NATIONAL NEWS - Construction began in April 2026, with completion scheduled for April 2028, subject to favourable construction conditions.
The project involves reconstructing approximately 4.57km of the existing single-carriageway road into a dual carriageway between the N2 and Faure Marine Drive (R44).
It also includes upgrades to adjoining roads, intersections, stormwater infrastructure and street lighting.
Construction progresses on multiple fronts
Work completed and under way includes earthworks and preparation for the new carriageway, identifying and relocating existing services, temporarily widening road shoulders and constructing the new right-hand-side carriageway.
Construction is being carried out in stages to limit traffic disruption and maintain access to affected properties.
Two-way traffic is intended to be maintained throughout the project using existing road sections, temporary diversions or completed portions of the upgraded carriageway.
Construction on Sir Lowry's Pass Road.
Intersection upgrades to improve road safety
The project includes the reconstruction of 17 intersections, 10 of which will be fitted with traffic signals. A roundabout will also be built at the intersection of MR108 and Faure Marine Drive, alongside additional traffic lanes and intersection improvements along Faure Marine Drive.
Kleineryk Road, Mountain Stream Road and Aqua Road will be upgraded and surfaced, while improvements are also planned for the Old MR108 and various access and service roads.
Other work includes installing street lighting along the full length of the upgraded MR108, improving stormwater drainage and constructing retaining structures.
New road signs, markings and safety barriers will further support safer travel.
Project creates employment and procurement opportunities
The road upgrade is also intended to support local economic participation through employment opportunities and procurement from targeted enterprises.
To date, the project has created 33 work opportunities against a target of 230. It has recorded 255 targeted-labour person-days, compared with a target of 29 000, while procurement expenditure with targeted enterprises has reached R2.5 million against a target of R81.2 million.
Roadworks on Sir Lowry's Pass Road.
Infrastructure investment targets long-term connectivity
Western Cape Minister of Infrastructure Tertuis Simmers said the project was about more than widening a road, highlighting its role in improving safety, strengthening connectivity and creating opportunities for people and businesses.
He said construction was progressing, with the department focused on delivering quality infrastructure while managing the impact on motorists, residents and businesses.
Simmers added that cooperation with the City of Cape Town and other stakeholders, including SANRAL regarding the future Firlands N2 Bypass interchange, was important to ensuring infrastructure investments addressed current needs while supporting future transport connectivity.
Motorists urged to take care in construction areas
The department acknowledged that construction along an existing road corridor could inconvenience motorists, residents and businesses.
Work will continue in phases, with traffic management measures implemented to maintain traffic flow and access wherever practicable.
Motorists are urged to exercise caution, follow temporary road signs and comply with traffic management arrangements for the duration of the construction period.